Morse Park Swimming Pool will be reopened in phases starting next Wednesday (Mar 22) as its conversion works have been completed, the Leisure and Cultural Department announced on Friday.
The indoor secondary pool will be reopened starting next Wednesday, while outdoor pools, including the 50-meter main pool, a diving pool, and three teaching pools, will be reopened starting from April 16.
The pool’s two-stage conversion project started in 2019, and the first stage of the work was expected to finish in March 2020.
But the work was delayed several times as the material supply was affected by the global
Covid-19 pandemic.